The California Energy Commission and the U.S. Department of Energy,
Office of Industrial Technologies BestPractices present:
ENERGY SOLUTIONS FOR CALIFORNIA INDUSTRY:
WAYS TO IMPROVE OPERATIONS AND PROFITABILITY
AUGUST 2001
CASE STUDY
BENEFITS
Saves $17,000 in annual energy costs
Improves equipment life
Improves productivity
Reduces maintenance costs
APPLICATIONS
Pump systems are widespread
and consume a significant
portion of the electricity used in
industrial plants. In some
cases, using Adjustable Speed
Drives (ASDs) provides an
effective means of matching
pumping output to system
requirements and can improve
operational reliability.
ABOUT THIS EVENT
The purpose of the Energy
Solutions for California events
is to provide a professional,
solutions-oriented environment
for industrial electricity users
who face serious challenges to
remaining operational and
profitable during the current
energy crisis. Industrial electricity
users have the opportunity
to receive unbiased information
and analytical tools that
can increase reliability and
manage short and long-term
production costs.
Pump System Improvement Saves Energy and Improves
Production at a Construction Aggregates Company
Summary
In 2000, Teichert Aggregates, Inc., with assistance from its local electric
utility, Sacramento Municipal Utility District (SMUD), improved the
pumping system at its Perkins aggregate processing plant in Sacramento,
California. The plant decided to evaluate its pumping system
because it was having problems maintaining stable flow and had excessive
maintenance requirements. Based on the evaluation, the plant
implemented a project that improved the pumping system’s effectiveness
by adding a magnetic induction Adjustable Speed Drive (ASD) to
the system. The total cost of the project was $34,000. With annual
energy savings of $17,000 (233,000 kWh), which represent 24% of the
pumping system’s power costs, and a grant of $15,000 for advanced
technologies from SMUD, the project’s simple payback was just under
13 months. The project also reduced maintenance costs, increased
pump bearing life and improved the plant’s process control.
ENERGY SOLUTIONS FOR CALIFORNIA INDUSTRY: Company/Plant Background
Teichert Aggregates, Inc. is one of California’s largest aggregates
companies. Established over a century ago, Teichert employs over
1,000 people. Teichert implements a full range of construction projects
ranging from construction of residential driveways, to freeways, subdivisions
and underground projects. The company also mines and
produces a variety of construction materials such as sand, gravel,
asphalt and concrete. Teichert Aggregates is one of the largest sand
and gravel producers in the U.S. and maintains several plants, including
the one in Sacramento, California.
The Perkins plant in Sacramento, California is one of Teichert Aggregate
Inc.’s largest construction aggregate facilities, producing concrete,
processed sand, gravel, crushed rock, and asphalt for a wide
variety of construction projects. The gravel production process uses a
feedwater system to help separate and wash the different types and
sizes of aggregates. Water is pumped up to the top of a 95-foot high
wash-down tower where it mixes with the aggregates. As the aggregates
flow down the tower, they pass across a series of screens and
are separated into fractions.
Project Overview
The wash-down tower was having problems related to stability of
water flow and excessive maintenance, so the plant had its pumping
system evaluated by an outside consultant. The pumping system that
feeds water into the wash-down tower is a 300-hp centrifugal pump
that is rated for 5600 gpm. The wash-down tower’s optimal flow rate
for reliable production is 4260 gpm. However, the plant had to throttle
the pump down to this level with a control valve because full flow
would flood the wash-down tower and interrupt production. However,
throttling the pump down to that level resulted in unstable flow and
caused the pump and its adjoining structures to shake violently.
The evaluation found that the unstable flow was the result of the pump
operating at a point that was far below the Best Efficiency Point (BEP)
on its performance curve. The violent shaking was due to cavitation
downstream around the discharge valve. The cavitation led to high
maintenance costs because it put excessive stress on the pump’s
bearings and could also erode the piping. The evaluation also found
that the pump drew a peak level of 247 kW when throttled to the 4260-
gpm levels.
Ways to Improve Operations and Profitability Project Implementation
The evaluation’s main recommendation was to install an ASD to match
the pumping system’s output to the plant’s requirements. The project
would replace the control valve operation with an ASD and was projected
to save energy and reduce maintenance. The motor was moved
back on its base and an actuator installed to allow for reduced pump
speed and better process control.
The plant manager decided on a special type of ASD that uses magnetic
induction. The plant manager selected this type of ASD because
it was at least as efficient as a Variable Speed Drive (VSD) at 90% or
higher of motor speed, which is the level at which the plant manager
expected to operate its pumping system. In addition, this ASD was
very rugged and simple, did not require an inverter-duty motor, extensive
wiring, or air conditioning.
Project Results
Thanks to the project’s implementation, the Teichert Aggregates plant
achieved positive benefits in terms of energy savings, reliability and
maintenance cost reductions. The ASD allowed the pumping system
to run at 4258 gpm without any unstable flow. Running at this level
reduced the pump’s annual electricity consumption by 233,000 kWh
(24% of its annual consumption), which translates into annual energy
savings of $17,000. Furthermore, the cavitation was eliminated,
dramatically reducing the vibration and lowering long-term maintenance
costs. The plant’s utility was so impressed with the reduction in energy
consumption that they issued a $15,000 rebate for the project. Since the
project’s cost was $34,000, the simple payback was slightly less than 13
months. In addition, the plant manager realized that if the impeller started
to wear, it could maintain exact process flow to the wash-down tower by
simply speeding up the pump.
Lessons Learned
Properly configuring a pumping system so that its capacity is suited to a
plant’s production requirements is extremely important. Pumps allow for
stable flow and consume the least amount of energy when they operate at
the BEP on their performance curves. When they do not operate at the
BEP, pumping systems can experience energy waste, unreliable production
and high maintenance costs. Different systems should be evaluated
to effectively match the available pumping capacity to production requirements,
while keeping pump operation at the BEP. For the Perkins aggregates
plant, a magnetic induction ASD was the appropriate and most costeffective
solution for the pumping system’s problems. The implementation
of this project led to important energy savings and allowed the plant’s
pumping system to operate more effectively.
United States Department of Energy’s
Office of Industrial Technologies BestPractices
BestPractices is part of the OIT’s Industries of the Future strategy, which helps the
country’s most energy-intensive industries improve their competitiveness. BestPractices
brings together the best-available and emerging technologies and practices to help
companies begin improving energy efficiency, environmental performance, and
productivity right now.
California Energy Commission
The California Energy Commission is the state’s primary energy policy and planning
agency. It is the California Energy Commission’s mission to assess, advocate, and act
through public/private partnerships to improve energy systems that promote a strong
economy and a healthy environment.
PROJECT PARTNERS
Teichert Aggregates, Inc. Sacramento, CA
Sacramento Municipal Utility District Sacramento, CA
MagnaDrive Corporation Seattle, WA
For Additional Information,
Please Contact:
U.S. Department of Energy
OIT Clearinghouse
Phone: (800) 862-2086
Fax: (360) 586-8303
E-mail: clearinghouse@ee.doe.gov
Web: www.oit.doe.gov